MIL-PRF-1/664F
NOTES: -Continued.
4. This test shall be performed during the initial production and once each succeeding 12-calendar months in
which there is production. An accept on zero defect sampling plan shall be used, with sample of three tubes
with an acceptance number of zero. In the event of failure, the test will be made as a part of conformance inspection,
part 2, with an acceptance level of 6.5 (see note 5 under Table I. The "12-calendar month" sampling plan shall be
reinstated after three consecutive samples have been accepted.
5. Nominal dimensions are for reference purposes only, and are not for inspection.
FIGURE 1. Outline drawing of electron tube type 5665. -Continued
NOTES
Referenced documents. In addition to MIL-PRF-1, this specification sheet sheet references MIL-STD-1311.
Changes from previous issue. The margins of this specification are marked with vertical lines to indicate where changes from
the previous issue were made. This was done as a convenience only and the Government assumes no liability whatsoever for
any inaccuracies in these notations. Bidders and contractors are cautioned to evaluate the requirements of this document
based on the entire content irrespective of the marginal notations and relationship to the previous issue.
Custodains:
Preparing activity:
Army - CR
DLA - CC
Navy - EC
Air Force - 11
(Project 5960-3713)
DLA - CC
Review activities:
Army - AR
Navy - AS, CG, MC, OS
Air Force - 99
NOTE: The activities listed above were interested in this document as of the date of this document. Since organizations and
responsibilities can change, you should verify the currency of the information above using the ASSIST Online database at
www.dodssp.daps.mil.